New construction prewire, 4,100 sq ft

Twenty-two drops, four access point locations, camera runs and a ventilated rack closet, all before drywall.

Home
New build, two levels, 4,100 sq ft
Area
San Mateo County, CA

Demonstration content

New construction prewire, 4,100 sq ft

The challenge

The builder's low-voltage package included six jacks, no ceiling access point locations and no camera runs, with the panel planned for an unventilated bedroom closet.

Existing setup

Framing complete, rough-in scheduled in two weeks.

What was installed

  • 22 Ethernet drops — two per office, desk and TV wall
  • Four ceiling drops for access points, including the patio
  • Six PoE camera runs at entries and the driveway
  • AV pathways and conduit to the theatre wall
  • Rack relocated to a ventilated utility room with dedicated power

Equipment

  • Cat6 cabling
  • In-wall AV conduit
  • 12U rack
  • 24-port PoE switch
  • Patch panel

Installation approach

Plan walked with the builder during framing, rough-in completed before insulation, trim-out and commissioning after paint.

Result

A home with technology infrastructure that did not need to be retrofitted — and spare pathways for the next decade of devices.